Progress Update - Shottery St. Andrews School

Together with our partners at Speller Metcalfe, R.O.Donaghey are pleased to share a progress update for our works at Shottery St. Andrews School, Stratford-upon-Avon.

Progress is well underway at Shottery, with our main works focusing around preparing the site and the footprint of the school. In order to achive this, we are currently undertaking a significant cut-and-fill exercise to level the ground in preparation for the formation of the foundations. Alongside the cut and fill, we have also begun the construction of the stone subbase to the school netball courts.

Progress at Shottery St. Andrews is moving swiftly, and we look forward to sharing another update with you soon.